EMT Practice Test
1. Question Content...
Question1: A driving relationship is _____________________.
Question3: Each of the following accurately describes total float in a schedule EXCEPT:
Question5: Which activity is drawn in the incorrect position?
Question6: Determine the driving activity for Activity 10001.
Question7: What problems can a soils engineer deal with on a project?
Question8: Determine the correct formula and date for the late start for Activity 9001.
Question11: What is the cycle time?
Question13: What is the free float for Activity F?
Question17: Time-scaled logic diagrams are
Question19: What is a key first step in developing a critical path method schedule?
Question23: In its simplest form, what is the main drawback of critical path method scheduling?
Question24: These are the activities on the critical path:
Question26: How many work days does it take to move the product from testing to sale?
Question28: Why does activity 11001 not show successor activities?
Question32: What is the result of a forward pass calculation?
Question35: Determine the correct formula and date for the late finish for Activity 2001.
Question37: Which of the following is NOT required when initially planning a project?
Question38: Which statement is true?
Question39: Assumptions made during the planning stage should be_____________.
Question41: What day would Activity C complete if the duration of Activity B was reduced to zero?
Question43: Determine the correct formula and date for the late finish for Activity 2002.
Question44: Resource planning must take all of the following into account except for:
Question46: Which is NOT an industry-recognized methodology for quantifying critical delay?
Question49: Is activity 7001 pictured correctly in the precedence diagram?
Question51: Identify the minimum project duration.
Question53: Determine the correct formula and date for the late finish for Activity 2002.
Question56: Who will receive the most benefit from a master schedule of the Spring Highway project?
Question59: The activity with the most total float is:
Question60: In a "crashed" schedule, which is a chain of activities that precede activity 2004?
Question62: What does the heavy, vertical line at "X" represent?
Question63: Identify the late finish to develop plans and specs.
Question64: Under which circumstance should one perform resource-leveling calculations?
Question65: For which of these delays should an owner grant a time extension?
Question66: What is the workweek period for this project?
Question68: What is accurate about Activity 7001 in the precedence diagram?
Question78: What is the remaining work duration of Active D?
